Severnaya 400 MW Gas Combined Cycle Power Plant
Project Description
The project consisted of construction of a new 400 MW combined cycle power plant. The Main Contractor was Mitsui-MHI Consortium. TML- Borova JV was the main subcontractor for civil works and mechanic, electric, instrument erection works.
Scope of Work
- 100.000 cub. meter Earth Works, Gravel Paving of 20.000 sq. meter, 4.000 sq. meter of Asphalt Concrete.
- 1.500 sq. meter Shotcrete for the foundation excavations of Pump Pit & Pump House.
- Construction of Turbine Generator Building, Generator Foundations, foundations of other equipment (1.000 nos L=14 m 400mm x 400mm RC piles), 100 tons of pipe racks, 2.000 tons of steel structure, 20.000 cub. meter of concrete.
- Construction of Cooling Water Intake Channel, Pump Pit & Pump House, Discharge Outfall, Water Treatment Facilities and Breakwater Structure.
- Railroad, Fencing, Sewage Water Treatment and Drainage System.
- Installation of Gas turbine of 370 tons, Generator of 300 tons, Waste Heat Recovery Steam Generator, Piping of 2.100 tons, Electrical Installation
- Supply and Erection of Condensate storage tank of 10.000 cub. meter, Fuel Storage tank of 5.000 cub. meter, Well Water tank of 400 cub. meter, Fire Water tank of 2.000 cub. meter, Potable Water tank of 60 cub. meter capacities.
Client
AZERENERGY
Date of Commencement
September, 2000
Date of Completion
November, 2002
Role of project management; Construction Mng. of TML Insaat Co., H.Gunes