Nergiz Shopping Center
The project consisted of a steel structure construction (on existing two storey reinforced car park), electrical and mechanical works of a shopping mall which is located in Baku. The building consists of 4 storey and total covered area is 8.000 sqm. The work covered steel construction, common areas (excluding shops) and facade architectural finishing works, mechanical, electrical and landscaping works.
Scope of Contract
- Thermal insulation,
- Water insulation,
- Roof cladding works.
- Transformer substations and MV switchgear,
- Diesel generators,
- Main distribution / MCC / Sub distribution boards,
- Lighting (Internal and External), Power distribution,
- Telecommunications,
- Fire Alarm and protection,
- Earthing and lightning protection,
- Low voltage systems (telephone, security/intruder alarm, CCTV).
- HVAC systems (heating/air conditioning/ventilation),
- Cold / Hot water supply, storage, piping,
- Sewage system collection pipes and pumps,
- HVAC ducting, insulation, piping works,
- Boiler / Chiller systems related works,
- Fire fighting system pumps and piping,
- Sprinkler system,
- Rainwater drainage,
- Elevators (Panoramic).
- Curtain wall glazing facade,
- GRC facade elements.
- Natural stone floor covering works,
- Wooden wall covering works,
- Gypsumboard suspended ceiling,
- Mineral wool suspended ceiling,
- 3 dimensional pre-formed lexan suspended ceiling,
- Floor and wall ceramic tiles,
- Decorative painting,
- Epoxy floor covering
Construction of steel structure system,
Execution of roof finishing works;
Installation of all electrical systems;
Installation of all mechanical systems (HVAC, plumbing, sanitation and sewage systems);
Execution of all exterior finishing works;
Execution of common areas interior finishing works;
Client
ISR INVESTMENTS CO. MMC.
Date of Commencement
February, 2006
Date of Completion
June, 2007